Pembangunan Pipa Terowongan Sodetan Ciliwung-KBT Capai 50 Persen
.
photo Ilustrasi - Beritajakarta.id

Ciliwung - KBT Penetration Channel Contruction Has Reached 50 Percent

The project of Ciliwung - East Flood Canal (KBT) penetration channel (sodetan) has reached 50 percent out of total lenght 1.2 kilometers. The line work for both tunnel in Kebon Nanas, Cipinang Besar Selatan Urban Village, up to arriving shaft on Jalan Otista III, Cipinang Cempedak Urban Village, Jatinegara has been done.

Both line as long as 600 meters have been installed.

Previouly, the first line project had been done in June 2015. The arriving shaft towards inlet of penetration channel is waiting for land buying process.

Basuki Hadimuljono, Minister of Public Works and Public Housing, said the penetration channel needs eight months to be finish. At this moment, the half project was already finished in four months.

Ciliwung-KBT Waterway Construction Project Constrained by Becakayu Highway Piles

"Both line as long as 600 meters have been installed. Next is connecting arriving shaft to the inlet," he said, Monday (10/12).

He has coordinated with Jakarta Provincial Government as his side needs land for the inlet. The land is still occupied by Bidara Cina residents.

According to him, the inlet project needs 1.1 ha in RW 04, 05, and 14 of Bidara Cina Urban Village. So far, mostly the residents have been relocated to Cipinang Besar Selatan flat, East Jakarta.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye393 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye389 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye347 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye322 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye315 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik